Watching brief by C Currie of CKCA during the breaching of the dam of Phillimore Lake found evidence for what is thought to have been the rare survival of a timber revetment facing the medieval mill dam. The timbers were sampled for dendrochronological dating. In the 1880s the Phillimore Lake dam had been rebuilt and enlarged to create a much larger lake, and the rebuilt dam was about 1.8m higher than the original and had a thin clay core. A few years later, in 1896, a second lake was created at Rowe’s Flash, and draining of this revealed a similar dam with a thin clay core. Leaks in both dams that had led to the works were thought to be the result of the poor standard of construction.
Year
2004
ID
60
NGR
SU995415
Periods
Borough
Organisation